LIU: HALF OF PARK PROJECTS FINISH BEHIND SCHEDULE : Audit Finds Months-Long Delays, Millions in Cost Overruns In Park Construction Projects
NEW YORK, N.Y. —City Comptroller John C. Liu today announced that the Parks Department’s failure to monitor its capital construction projects had allowed almost half of those projects to finish late and 10% to go significantly over budget in Fiscal Years 2010 and 2011.
“New Yorkers and visitors alike love our parks. Repairs and upgrades must be better managed not only to reduce wasteful spending, but also to minimize the duration of park closures,”Comptroller Liu said. “The Parks Department can do better.”
In FY2010-FY2011, the Parks Department completed 315 capital construction projects, at a cost of $496.3 million. Comptroller Liu’s audit found that:
149 (47%) of those projects finished late. The projects were 218 days late on average. These late projects were supposed to have been complete within 284 days on average, so the delays resulted in almost doubling the length of time planned for completion.
30 projects combined to rack up $10 million in cost overruns, over and above the additional $8.6 million in contingency allowances for overruns that they burned through. The projects had been budgeted at a combined cost of $69.6 million.
Despite spending $4 million to correct consultants’ design errors and omissions on various projects, the Parks Department did not use its right to try and recoup the money.
Comptroller Liu’s Audit Bureau launched the audit in response to numerous complaints from New Yorkers, including calls to the Comptroller’s 212-NO-WASTE hotline, and after independently assessing that an examination of the agency’s capital projects was warranted.
The audit recommended several steps that the Parks Department should take to better ensure that projects are completed on time and within budget. For example, the audit recommended that the Parks Department flag projects for priority completion so that delayed work can be expedited.
Today’s audit is available for download here: http://www.comptroller.nyc.
The complete list of projects that were delayed or overbudget is available in the audit’s appendix.
Parks Projects That Were Significantly Overbudget And Delayed
| Project Description | Borough | Delay Days | Over Budget Amt |
| POE PARK VISITORS CENTER | Bronx | 578 | $ 1,234,802 |
| SOUNDVIEW PARK – CONSTR OF | Bronx | 693 | $ 777,884 |
| EDENWALD PLAYGROUND | Bronx | 187 | $ 163,000 |
| CHARLTON GARDEN PLGD | Bronx | 213 | $ 139,150 |
| SCHOOLYARDS @ PS105K, PS 112, PS 205, PS 247 | Brooklyn | 555 | $ 572,000 |
| KAISER PARK – REC BLDG | Brooklyn | 930 | $ 449,674 |
| ROBERT E. VENABLE PARK | Brooklyn | 182 | $ 435,990 |
| ROBERT E. VENABLE PARK | Brooklyn | 421 | $ 161,028 |
| RIVERSIDE PARK | Manhattan | 366 | $ 1,753,617 |
| PAVEMENTS, SIDEWALKS | Manhattan | 653 | $ 800,000 |
| UNION SQUARE PK – CONSTR OF | Manhattan | 325 | $ 309,454 |
| SCHOOLYARDS @ PS 129Q, PS 79, JHS 25, PS 159 | Queens | 53 | $ 182,000 |
| SCHOOLYARDS @ PS 116Q & IS 238 | Queens | 284 | $ 100,949 |
| CONSTR OF TUSCAN GARDEN & LEMON HOUSE, SNUG HARBOR | Staten Island | 1071 | $ 804,367 |
Visit www.comptroller.nyc.gov
- New York Attorney General James Secures Reimbursements for T-Mobile Customers Whose Rates Were Unjustly Raised
- নিউইয়র্কে বাংলাদেশ সোসাইটির নির্বাচনে কুনু-ফিরোজ পরিষদের সাত দফা ইশতেহার ঘোষণা; কমিউনিটি সেন্টার প্রতিষ্ঠা, সাশ্রয়ী ফিউনারেল সেবা, বিমানের সরাসরি ফ্লাইট ও আর্থিক স্বচ্ছতায় অঙ্গীকার
- ফিলিস্তিনিদের আত্মনিয়ন্ত্রণের অধিকারের প্রতি বাংলাদেশের পূর্ণ সমর্থন: জাতিসংঘে রাষ্ট্রদূত আইরিন খান
- নিউইয়র্কে বাংলাদেশ সোসাইটির নির্বাচনে প্রথমবারের মতো বিতর্ক, গুরুত্ব পেল স্বচ্ছতা ও জবাবদিহি
- New York Attorney General James Warns New Yorkers About AI-Generated Election Misinformation Ahead of November Elections
- Bangladesh calls for global treaty to protect victims of crimes against humanity
- নিউইয়র্কে জাতিসংঘে মুহাম্মদ নওশাদ জমির এমপি: মানবতাবিরোধী অপরাধ প্রতিরোধে শক্তিশালী আন্তর্জাতিক সনদ প্রণয়নের আহ্বান
- সোশ্যাল মিডিয়ার তথ্য গোপন করলে যুক্তরাষ্ট্রের ভিসা প্রত্যাখ্যান, আবেদনপত্রে চাওয়া তথ্য সঠিক ও সম্পূর্ণভাবে দেওয়ার নির্দেশনা মার্কিন দূতাবাসের